Energy Reserve 1

We are developing Energy Reserve 1 as a fast-start, dispatchable power generation facility, to help provide capacity security, in a world of increasing intermittent renewable energy supply

Helping provide increased energy security and system stability to our customers

Lochard Energy is developing a new, fast start dispatchable energy generation facility, near Benalla in north-east, Victoria, called Energy Reserve 1 (ER1).

ER1 is being designed to use highly efficient natural gas reciprocating engines (GPG) and batteries (BESS) to provide a rapid supply of electricity at times when demand for energy is high, or when other forms of energy generation are not available to meet market demand.

This type of power plant, sometimes referred to as a “peaker”, typically only operates for a few hours or days at a time.

A planning application is being lodged to enable either or both technologies to be commercially considered at a later date on the basis of customer, market, social and regulatory requirements.

Proposed visualisations

Project enquiries

Lochard Energy understands that neighbours and the community may have questions or concerns regarding the proposed Energy Reserve 1 Project and we take community engagement and feedback very seriously. We welcome the opportunity to directly discuss any queries about the Project.

Please email your enquiry to and an appropriate team member from our project team will contact you, or alternatively fill out the form below.

    Project status

    Connection enquiry

    Complete 

    Site environmental assessments

    Complete

    EES and EPBC self assessment

    Complete

    Cultural heritage management plan

    Approved

    }
    Development application

    In progress

    }
    Connection agreement

    In progress

    [
    Financial investment decision & start of construction

    2024/2025

    [
    Commercial operation date

    2026/2027